Report Summary
Overall results relating to the effective management of finance and procurement activities of the United Nations Global Service Centre were initially assessed as unsatisfactory. Implementation of one critical and four important recommendations remains in progress.
Issue Date
Entity
DFS
Report No
2014/155
Report Type
Audit Report
Available Date
Withhold available date
No
Assignment No
AP2014/617/02
Number of important recommendations
5
Number of important recommendations implemented
4
Number of critical recommendations
1
Number of critical recommendations implemented
1
Confidentiality
Non Confidential