Report Summary

Overall results relating to effective management of local procurement activities in MINUSTAH were initially assessed as unsatisfactory. Implementation of one critical and five important recommendations remains in progress

Issue Date
Entity
MINUSTAH
Report No
2013/081
Report Type
Audit Report
Available Date
Withhold available date
No
Editor Report Title
USE REDACTED VERSION FOR DISCLOSURE ON WEBPAGE
Assignment No
AP2012/683/03
Number of important recommendations
7
Number of important recommendations implemented
7
Number of critical recommendations
2
Number of critical recommendations implemented
2
Confidentiality
Non Confidential
Ratings
Unsatisfactory