Audit of management of technical cooperation projects in the Economic Commission for Africa

Report Summary

Overall results relating to the effective management of technical cooperation projects were initially assessed as partially satisfactory. Implementation of three important recommendations remains in progress.

Issue Date
Entity
ECA
Report No
2016/066
Report Type
Audit Report
Available Date
Withhold available date
No
Assignment No
AN2015/710/01
Number of important recommendations
3
Number of important recommendations implemented
3
Number of critical recommendations
0
Number of critical recommendations implemented
0
Confidentiality
Non Confidential
Ratings
Partially Satisfactory
Authored on