Report Summary
While cluster coordination and project implementation were effectively managed by the country office, improvements were needed in work plan implementation, business continuity planning and access control to office premises.
Issue Date
Entity
OCHA
Report No
2018/045
Report Type
Audit Report
Available Date
Withhold available date
No
Assignment No
AN2017/590/03
Number of important recommendations
6
Number of important recommendations implemented
3
Number of critical recommendations
0
Number of critical recommendations implemented
0
Confidentiality
Non Confidential
Authored on