Report Summary
There were critical deficiencies in controls and management oversight arrangements over procurement which could adversely impact the achievement of regional objectives in supply and asset management.
Issue Date
Entity
UNHCR
Report No
2018/005
Report Type
Audit Report
Available Date
Withhold available date
No
Assignment No
AR2017/111/05
Number of important recommendations
7
Number of important recommendations implemented
6
Number of critical recommendations
1
Number of critical recommendations implemented
1
Confidentiality
Non Confidential
Authored on