Report Summary
Overall results relating to the effective implementation of the mandate of the Transportation and Movement Integrated Control Centre in the Regional Service Centre in Entebbe and the Department of Field Support were initially assessed as partially satisfactory. Implementation of five important recommendations remains in progress.
Issue Date
Entity
DFS
Report No
2014/038
Report Type
Audit Report
Available Date
Withhold available date
No
Assignment No
AP2013/616/04
Number of important recommendations
5
Number of important recommendations implemented
2
Number of critical recommendations
0
Number of critical recommendations implemented
0