Internal Audit Reports
Notes
(a) Report availability: As of 1 June 2013, internal audit reports issued by the Office of Internal Oversight Services are available 30 days following issuance of the report.
(b) Implementation rates of recommendations
The attached spreadsheet provides critical and important recommendation implementation rates for each of the final audit reports posted on the website (as of the most recent quarterly follow-up exercise).
Issue Date | Entity | Report Number | Report Title | Avail Date | No. of Important Recommendations | No. of Critical Recommendations | Report/Available Date | Confidentiality |
---|---|---|---|---|---|---|---|---|
22 February 2024 | UNSOM, UNSOS | 2024/006 | Audit of the safety and security of national staff in the United Nations Assistance Mission in Somalia (UNSOM) and the United Nations Support Office in Somalia (UNSOS) | 22 February 2024 | 6 | 0 | Withheld | Confidential |
24 December 2024 | DMSPC, DOS | 2024/086 | Audit of the identity management system in the United Nations Secretariat | 24 December 2024 | 9 | 0 | Withheld | Confidential |
24 January 2023 | MINUSMA, DOS | 2023/001 | Audit of unmanned aerial systems at the United Nations Multidimensional Integrated Stabilization Mission in Mali | 24 January 2023 | 9 | 0 | Withheld | Confidential |
21 December 2023 | UNIFIL | 2023/080 | Audit of political affairs activities in the United Nations Interim Force in Lebanon | 21 December 2023 | 1 | 0 | Withheld | Confidential |
29 March 2024 | DMSPC, DOS | 2024/010 | Audit of security of electronic mail at the United Nations Secretariat | 29 March 2024 | 9 | 0 | Withheld | Confidential |
13 June 2013 | ESCAP | 2013/051 | Audit of the Economic and Social Commission for Asia and the Pacific | 15 July 2013 | 6 | 0 |
![]() |
Non Confidential |
21 August 2013 | ITC | 2013/067 | Audit of project management at the International Trade Centre | 20 September 2013 | 6 | 0 |
![]() |
Non Confidential |
09 October 2013 | UN-HABITAT | 2013/083 | Audit of recruitment of staff and other personnel at the United Nations Human Settlements Programme | 08 November 2013 | 4 | 0 |
![]() |
Non Confidential |
19 November 2013 | ICTR | 2013/097 | Audit of language services in the International Criminal Tribunal for Rwanda | 19 December 2013 | 6 | 0 |
![]() |
Non Confidential |
09 December 2013 | UNMIL | 2013/117 | Audit of accounts receivable and payable in the United Nations Mission in Liberia | 08 January 2014 | 5 | 0 |
![]() |
Non Confidential |